CLARKSVILLE, Tenn. – Gas and Water utility construction contractors will begin a 4-5 month long water main improvement project on Tuesday, Jan. 14, on Calvert Drive and vicinity including Center Road, Shady Lane, Hilltop Court and Lewter Drive. Weather permitting, work will commence daily on weekdays during daylight hours.
The general scope of the work includes installing over 5,000 linear feet of six inch water main line, fire hydrant replacement, water service line transfer to the new water main, road boring, digging, concrete repair and road paving.
Water outages, low water pressure and road closures will be announced as the work progresses.
Please pardon the disturbance in the neighborhood as the upgrade activities take place.
For more information, please contact Y’hanna Perez-Ortiz, P.E., Civil Engineer, at the Clarksville Gas and Water Engineering Department, 931-645-7418.