Posted on: July 5, 2023

Clarksville moves forward on sidewalk projects, receives $450,000 grant

a new sidewalk running along S Jordan Dr in North Clarksville

CLARKSVILLE, TN - The City of Clarksville has more than 16 sidewalk projects under way to improve livability and walkability in Clarksville, many of which are preparing to enter the final phases of completion. 

One of these projects, located on Greenwood Avenue, recently received a $450,000 construction grant from the Tennessee Department of Transportation (TDOT).

“Our sidewalk improvement program is a vital component of the City's overall Transportation 2020+ Master Plan," said Clarksville Mayor Joe Pitts. "We fully understand how important it is for the safety of our residents and livability of our neighborhoods, and we are committed to staying on track with it."

Sidewalk projects can typically be divided into three phases; design, right-of-way acquisition and construction. Here’s how current projects are progressing.

Design Phase

During the design phase, sidewalk projects undergo surveys, utility coordination and planning by engineers to ensure the project can move forward quickly and efficiently.

The following projects are currently in this phase:

  • Tiny Town Road

  • Ringgold Road

  • Richview Road

  • E Street

  • Beech Street

  • Thornberry Road to Cardinal Lane

  • Crossland Avenue

  • State Highway 48/13 Phase 2

  • Hazelwood Road

Right-of-Way Acquisition

In the right-of-way acquisition phase, the city conducts title searches, property appraisals and individual property negotiation in order to acquire the land needed to create new sidewalks.

Projects undergoing right-of-way acquisition include:

  • Greenwood Avenue

  • Peachers Mill Road

  • Glenhurst Way to Meriweather Road

  • Golden Eagle Way to Northeast schools complex

  • Old Russellville Pike

  • North Liberty Church Road/ Appleton Drive

  • Roedeer Drive

Construction

The final phase of a sidewalk project is construction, during which the new sidewalk is actually implemented. No projects are currently in the construction phase; however, several projects are preparing to enter this step, according to the Street Department.

For updates on sidewalks, as well as other infrastructure projects, citizens can visit the Transportation 2020+ Plan website.

Facebook Twitter Email

Other News in All News

City Hall

City offices to close for Thanksgiving

Posted on: November 20, 2023

Celebrate Riverfest’s finale

Posted on: September 7, 2023
City Hall

City Court Clerk to have new hours

Posted on: July 25, 2023
Screenshot 2023-07-13 141553

Spring Alley closed for utility work

Posted on: July 13, 2023
Swan Lake Pool

Outdoor pool season returns May 27

Posted on: May 25, 2023
A veterans memorial located in Downtown Clarksville

Vietnam War Veterans Day Message

Posted on: March 31, 2023
O11

Clarksville elected officials sworn in

Posted on: January 5, 2023
Weather Report Jan. 6

City offices working remotely

Posted on: January 6, 2022